Demolition of abandoned factory buildings
1、The area of the factory building is: 60m×30m
2、the area of the production line is: 50m×24m.
Through reasonable layout, the equipment can just be mobile crushing and screening in the factory building.
Mobile Vertical Shaft Crusher Plant
It is equipped with vibrating feeder, electric control system, variable-speed feeder and independent constant-speed pre-screening structure as standard. The maximum output is 500t/h, and the large crushing ratio can provide finished materials with perfect granular shape.
Customer Reviews
Not only can all kinds of construction waste be broken into large and small particles, but also the steel bar can be separated from the concrete, and then removed from the material by the iron remover.
The dismantled construction waste is evenly fed by the vibrating feeder through the silo, and transported to the special crusher for construction waste for crushing.
The crushed material is screened by a vibrating screen to obtain:0-6mm, 6-14mm, 14-36mm.The aggregates of three different specifications are transported to each finished product stack by the belt conveyor.
It can produce an average of 190-220 tons per hour. Excluding equipment and labor costs, the daily profit of this production line is very considerable.